ProjectCompleted
SOS Children's Village Lekenik — solarisation
A 100 kW solar power plant in permanent operation; a further 250 kW remains a planned second phase.
About the record
According to ZEZ's March 2026 announcement, the first phase of installing solar power at the community centre and kindergarten of SOS Children's Village Lekenik, with a capacity of 100 kW, received a permanent operating permit. A further 250 kW across 15 houses was announced as a second phase. The total 350 kW is therefore not presented as already installed.
Key data
- Type
- Project
- Status
- Completed
- Location
- SOS Children's Village Lekenik
- Area
- Sisak-Moslavina
- Spatial extent
- Community centre and kindergarten; a second phase is planned for 15 houses
- Lead organisation
- SOS Children's Villages Croatia; implemented by ZEZ with donor partners
- Period
- First phase confirmed in permanent operation in March 2026.
- Funding
- €340,000 donation for a two-phase project
Indicators
- 100 kW · permanent operation
- 250 kW · planned
- 15 houses · second-phase plan
Content reviewed